The Building Warrant Application process is dependant on the council’s current workload but typically takes between 4-6 weeks from submission to approval.
Once the Building Warrant Application has been approved, work may start on site.
When your project is finished you should apply to Building Control for a Completion Certificate.
Please note that in addition to our own fees, the following may also be required: –
- Structural Engineer to provide structural details and SER Certificate. Should you decide to use a prefabricated timber frame supplier, they will normally provide an SER Certificate as part of their service.
- Energy consultant to provide SAP Calculations for thermal & energy efficiency.
We would be happy, as part of our service, to obtain quotations for these.
To find out how much a Building Warrant Application will cost, please click on the relevant link below: –
Perth & Kinross Council Warrant Fees
City of Edinburgh Council Warrant Fees
Dundee City Council Warrant Fees